The project team is currently addressing concerns raised at the Public Hearing. The schedule going forward is as follows:
Note that all dates are tentative and subject to change.
Winter 2022
- Plan to hold a public informational meeting
Spring 2023
- Final Revision to Environmental Assessment (EA)
- Receive Finding of No Significant Impact (FONSI)
Spring 2023 to Fall 2028
- Initiate Final Design Phase
- Right-of-Way Acquisitions/Easements
- Environmental Permitting
Anticipated start of Spring 2027
- Exit 7 Construction Phase (Manchester 16099B)
Anticipated start of Spring 2029
- Exit 6 Construction Phase (Manchester 16099A)
|